1 sectionAdd a section for each different pour — footings, columns, piers, walls — and give each one a quantity. Everything is combined into one concrete order.
Section 01 of 01
Wall, footing, pad, beam, curb, or any other rectangular pour.
How many identical pours of this section.
An editable planning allowance for waste, over-excavation and placement contingencies — NRMCA guidance suggests roughly 4–10% depending on job conditions, not one universal figure.
Pouring only a slab? The Concrete Slab Calculator is built for flatwork, with thickness-based input, bag counts, truckload planning and cost.
Advanced options
Bagged concrete
Optional. Bag count is based on the mixed yield you enter, not bag weight — different manufacturers' same-weight bags don't necessarily yield the same mixed volume.
From your bag's product data sheet — use your own product's stated yield for anything beyond a rough estimate.
Ready-mix cost
Entirely optional — no price is pre-filled. A material-only estimate from the unit price you enter. Delivery, minimum-load and short-load fees, pumping, labor, taxes and other charges are not included.
Your Estimate
Add a concrete section with its dimensions and quantity to see your estimate.
How It's Calculated
Methodology
Add a concrete section with its dimensions and quantity to see the formula breakdown.
Assumptions & Accuracy
Volume comes straight from the dimensions you enter — length × width × height for rectangular pours, π × r² × height for round ones, and the ring area for hollow round ones. Every section's volume is multiplied by its quantity and summed at full precision before one project-level order allowance is applied. Optional bag counts and cost use only the figures you enter.
Material quantity estimate only. This calculator converts dimensions you provide into concrete volume. It does not size footings, columns, walls or slabs; determine reinforcement, concrete strength, bearing capacity, frost depth, or code compliance; and is not a substitute for project drawings or a qualified professional.
Project Guide
How to use the Concrete Calculator
Add one section for each different pour in your job, choose its shape, enter the dimensions you already have, and set how many identical pours of that shape you need. A deck might be eight piers plus two pads; a foundation might be a run of footings plus several columns. The calculator combines them all into one total and one concrete-to-order figure, so you place a single order instead of adding up separate calculations by hand.
Rectangular, round and hollow round pours
Rectangular covers anything box-shaped — a wall, a strip or pad footing, a beam, a curb. Volume is length × width × height (or depth).
Round covers anything cylindrical — a column, a pier, a round footing, a Sonotube-formed pour. You enter the diameter because that's what you can actually measure across a hole or a form; the calculator halves it to get the radius, then uses π × r² × height.
Hollow round covers ring-shaped pours — a circular wall, a tube, a ring beam. It subtracts the empty core: π × (outer radius² − inner radius²) × height. The inner diameter must be smaller than the outer one.
How multiple sections are combined
Each section's per-unit volume is multiplied by its quantity, and those section totals are added together at full precision. Only then is the order allowance applied. Nothing is rounded section by section along the way — rounding each piece first and then adding is how estimates drift. Eight piers of 0.0873 yd³ each, for example, total 0.70 yd³, but rounding each to 0.09 yd³ first and summing would wrongly give 0.72 yd³.
What the order allowance means
Field dimensions rarely match plan dimensions exactly — forms deflect, excavations come out slightly oversize, and some concrete is always lost to spillage. NRMCA's technical guidance (CIP 8, “Discrepancies in Yield”, and CIP 31) recommends ordering roughly 4–10% over the calculated volume for these contingencies, framed as a range rather than a fixed number: controlled, repetitive placements sit at the low end, while irregular or hand-dug work needs more. The 5% default sits in that range and is fully editable — there is no universally correct figure.
Bagged concrete vs. ready-mix
Ready-mix arrives by truck and is ordered in cubic yards or cubic meters, which suits larger pours. Bagged concrete is mixed on site and suits smaller jobs — a handful of piers, a small pad, a repair. Neither is universally better; it depends on your volume, site access and your supplier's minimum order.
If you enter a bag yield, the bag count divides your order volume by the manufacturer's stated mixed yield — the volume one bag makes once water is added — never by the bag's dry weight. Two bags of the same weight from different manufacturers don't necessarily yield the same volume, so check your own product's data sheet.
Which concrete calculator should I use?
Use this calculator when your job has more than one shape, or repeated objects you want to multiply — footings, columns, piers, walls, rings. Its job is combining different pours into a single order.
Use the Concrete Slab Calculator when you're pouring flatwork. It's built around slab thinking — area and thickness — and adds slab-specific planning this page deliberately leaves out: truckload planning and a ready-mix-versus-bagged cost comparison.
Footings only? Use the dedicated Concrete Footing Calculator for footing-specific terminology, diagrams, and material planning.
Building solid concrete steps? Use the dedicated Concrete Stairs Calculator for stair-specific geometry and material planning.
Why post volume is not subtracted
A round section calculates the full volume of the hole or form. If a post occupies part of that space, this calculator does not subtract its volume, so the result may be higher than the concrete actually placed. For post-setting jobs where displacement matters, use a dedicated post-hole calculation rather than treating this result as an exact concrete requirement.
Material estimate vs. structural design
Everything here is quantity estimating. The calculator takes dimensions you already have — from your drawings, your plans, or a professional — and converts them into concrete volume. It does not tell you how big a footing should be, how deep to go below frost, what a column needs to carry a load, what concrete strength to specify, or what reinforcement is required. Those are design decisions that belong to your project documents or a qualified professional.
Worked Examples
Illustrative values only — enter your own project's dimensions above for a real estimate.
Example 01
A mixed pour: one rectangular footing, four piers and two columns, with a 5% order allowance.
Inputs
- Rectangular footing: 10 ft × 4 ft × 1 ft, quantity 1
- Piers: 12 in diameter × 3 ft deep, quantity 4
- Columns: 2 ft diameter × 10 ft high, quantity 2
- Order allowance: 5%
Calculation
- Footing: 10 × 4 × 1 = 40 ft³
- Piers: π × (0.5 ft)² × 3 = 2.3561945 ft³ each × 4 = 9.4247780 ft³
- Columns: π × (1 ft)² × 10 = 31.4159265 ft³ each × 2 = 62.8318531 ft³
- Calculated volume: 40 + 9.4247780 + 62.8318531 = 112.2566310 ft³
- Concrete to order: 112.2566310 × 1.05 = 117.8694626 ft³
- In cubic yards: 117.8694626 ÷ 27 = 4.3655357 yd³
Result
Practical interpretation
Example 02
A single rectangular section in Metric: 3 m × 2 m × 0.15 m, plus four 0.4 m piers, 5% allowance.
Inputs
- Rectangular: 3 m × 2 m × 0.15 m, quantity 1
- Piers: 0.4 m diameter × 2.5 m, quantity 4
- Order allowance: 5%
Calculation
- Rectangular: 3 × 2 × 0.15 = 0.9 m³
- Piers: π × (0.2 m)² × 2.5 = 0.3141593 m³ each × 4 = 1.2566371 m³
- Calculated volume: 0.9 + 1.2566371 = 2.1566371 m³
- Concrete to order: 2.1566371 × 1.05 = 2.2644689 m³
Result
Practical interpretation
FAQ
How do I calculate how much concrete I need?
How many cubic yards of concrete do I need?
Can I combine several concrete pours in one calculation?
How do I calculate concrete for a round column or pier?
How do I calculate concrete for a footing?
Does this calculator subtract the volume of a post from a post hole?
How much extra concrete should I order?
How many bags of concrete do I need?
Should I use this calculator or the Concrete Slab Calculator?
Does this calculator estimate cost?
Related Calculators
Concrete & Masonry
Concrete Slab Calculator
Estimate how much concrete to order for a rectangular or circular slab, plus optional bags, truckloads, and material cost.
Concrete & Masonry
Concrete Block Calculator
Estimate concrete block (CMU) quantity, mortar bags, and material cost for a block wall.
Concrete & Masonry
Brick Calculator
Estimate how many bricks you need for a wall, plus optional mortar, pallets, and material cost.
Concrete & Masonry
Concrete Footing Calculator
Estimate concrete for continuous strip footings, rectangular isolated footings and round footings. Combine multiple footing sections into one concrete order with optional bag, truckload and cost planning.
Concrete & Masonry
Concrete Stairs Calculator
Estimate concrete volume for solid poured concrete stairs or steps using rise, run, width and number of concrete steps, with optional bags, truckload and cost planning.