Concrete Calculator

Estimate concrete volume for footings, columns, piers, walls and other pours. Add every section of the job to one project and get a single concrete order.

Your Project

Shape reference diagrams
Rectangular concrete section drawn as a box, with length, width and height or depth labeledLengthHeight / depthWidth
Wall, footing, pad or beam — V = L × W × H
Solid round concrete section drawn as a cylinder, with diameter and height or depth labeledDiameterHeight / depth
Column, pier or round footing — V = π × r² × H
Hollow round concrete section drawn as a ring, with outer diameter, inner diameter and height labeledOuter diameterInner ⌀Height
Ring, tube or circular wall — V = π × (R² − r²) × H

Concrete Sections

1 section

Add a section for each different pour — footings, columns, piers, walls — and give each one a quantity. Everything is combined into one concrete order.

Section 01 of 01

Wall, footing, pad, beam, curb, or any other rectangular pour.

How many identical pours of this section.

%

An editable planning allowance for waste, over-excavation and placement contingencies — NRMCA guidance suggests roughly 4–10% depending on job conditions, not one universal figure.

Pouring only a slab? The Concrete Slab Calculator is built for flatwork, with thickness-based input, bag counts, truckload planning and cost.

Advanced options
Bagged concrete

Optional. Bag count is based on the mixed yield you enter, not bag weight — different manufacturers' same-weight bags don't necessarily yield the same mixed volume.

QUIKRETE Concrete Mix:
ft³/bag

From your bag's product data sheet — use your own product's stated yield for anything beyond a rough estimate.

Ready-mix cost

Entirely optional — no price is pre-filled. A material-only estimate from the unit price you enter. Delivery, minimum-load and short-load fees, pumping, labor, taxes and other charges are not included.

$

Your Estimate

Add a concrete section with its dimensions and quantity to see your estimate.

How It's Calculated

Methodology

Add a concrete section with its dimensions and quantity to see the formula breakdown.

Assumptions & Accuracy

Volume comes straight from the dimensions you enter — length × width × height for rectangular pours, π × r² × height for round ones, and the ring area for hollow round ones. Every section's volume is multiplied by its quantity and summed at full precision before one project-level order allowance is applied. Optional bag counts and cost use only the figures you enter.

Material quantity estimate only. This calculator converts dimensions you provide into concrete volume. It does not size footings, columns, walls or slabs; determine reinforcement, concrete strength, bearing capacity, frost depth, or code compliance; and is not a substitute for project drawings or a qualified professional.

Project Guide

How to use the Concrete Calculator

Add one section for each different pour in your job, choose its shape, enter the dimensions you already have, and set how many identical pours of that shape you need. A deck might be eight piers plus two pads; a foundation might be a run of footings plus several columns. The calculator combines them all into one total and one concrete-to-order figure, so you place a single order instead of adding up separate calculations by hand.

Tip: Each dimension has its own unit picker, so you can enter a footing as 6 ft × 2 ft × 12 in without converting anything to decimal feet yourself.

Rectangular, round and hollow round pours

Rectangular covers anything box-shaped — a wall, a strip or pad footing, a beam, a curb. Volume is length × width × height (or depth).

Round covers anything cylindrical — a column, a pier, a round footing, a Sonotube-formed pour. You enter the diameter because that's what you can actually measure across a hole or a form; the calculator halves it to get the radius, then uses π × r² × height.

Hollow round covers ring-shaped pours — a circular wall, a tube, a ring beam. It subtracts the empty core: π × (outer radius² − inner radius²) × height. The inner diameter must be smaller than the outer one.

How multiple sections are combined

Each section's per-unit volume is multiplied by its quantity, and those section totals are added together at full precision. Only then is the order allowance applied. Nothing is rounded section by section along the way — rounding each piece first and then adding is how estimates drift. Eight piers of 0.0873 yd³ each, for example, total 0.70 yd³, but rounding each to 0.09 yd³ first and summing would wrongly give 0.72 yd³.

What the order allowance means

Field dimensions rarely match plan dimensions exactly — forms deflect, excavations come out slightly oversize, and some concrete is always lost to spillage. NRMCA's technical guidance (CIP 8, “Discrepancies in Yield”, and CIP 31) recommends ordering roughly 4–10% over the calculated volume for these contingencies, framed as a range rather than a fixed number: controlled, repetitive placements sit at the low end, while irregular or hand-dug work needs more. The 5% default sits in that range and is fully editable — there is no universally correct figure.

Bagged concrete vs. ready-mix

Ready-mix arrives by truck and is ordered in cubic yards or cubic meters, which suits larger pours. Bagged concrete is mixed on site and suits smaller jobs — a handful of piers, a small pad, a repair. Neither is universally better; it depends on your volume, site access and your supplier's minimum order.

If you enter a bag yield, the bag count divides your order volume by the manufacturer's stated mixed yield — the volume one bag makes once water is added — never by the bag's dry weight. Two bags of the same weight from different manufacturers don't necessarily yield the same volume, so check your own product's data sheet.

Which concrete calculator should I use?

Use this calculator when your job has more than one shape, or repeated objects you want to multiply — footings, columns, piers, walls, rings. Its job is combining different pours into a single order.

Use the Concrete Slab Calculator when you're pouring flatwork. It's built around slab thinking — area and thickness — and adds slab-specific planning this page deliberately leaves out: truckload planning and a ready-mix-versus-bagged cost comparison.

Footings only? Use the dedicated Concrete Footing Calculator for footing-specific terminology, diagrams, and material planning.

Building solid concrete steps? Use the dedicated Concrete Stairs Calculator for stair-specific geometry and material planning.

Why post volume is not subtracted

A round section calculates the full volume of the hole or form. If a post occupies part of that space, this calculator does not subtract its volume, so the result may be higher than the concrete actually placed. For post-setting jobs where displacement matters, use a dedicated post-hole calculation rather than treating this result as an exact concrete requirement.

Material estimate vs. structural design

Everything here is quantity estimating. The calculator takes dimensions you already have — from your drawings, your plans, or a professional — and converts them into concrete volume. It does not tell you how big a footing should be, how deep to go below frost, what a column needs to carry a load, what concrete strength to specify, or what reinforcement is required. Those are design decisions that belong to your project documents or a qualified professional.

Worked Examples

Illustrative values only — enter your own project's dimensions above for a real estimate.

Example 01

A mixed pour: one rectangular footing, four piers and two columns, with a 5% order allowance.

Inputs

  • Rectangular footing: 10 ft × 4 ft × 1 ft, quantity 1
  • Piers: 12 in diameter × 3 ft deep, quantity 4
  • Columns: 2 ft diameter × 10 ft high, quantity 2
  • Order allowance: 5%

Calculation

  • Footing: 10 × 4 × 1 = 40 ft³
  • Piers: π × (0.5 ft)² × 3 = 2.3561945 ft³ each × 4 = 9.4247780 ft³
  • Columns: π × (1 ft)² × 10 = 31.4159265 ft³ each × 2 = 62.8318531 ft³
  • Calculated volume: 40 + 9.4247780 + 62.8318531 = 112.2566310 ft³
  • Concrete to order: 112.2566310 × 1.05 = 117.8694626 ft³
  • In cubic yards: 117.8694626 ÷ 27 = 4.3655357 yd³

Result

4.37 yd³ concrete to order (117.87 ft³).

Practical interpretation

Three different shapes and seven separate pours become one number to give a supplier — which is the whole reason to use this page instead of running three calculations separately.

Example 02

A single rectangular section in Metric: 3 m × 2 m × 0.15 m, plus four 0.4 m piers, 5% allowance.

Inputs

  • Rectangular: 3 m × 2 m × 0.15 m, quantity 1
  • Piers: 0.4 m diameter × 2.5 m, quantity 4
  • Order allowance: 5%

Calculation

  • Rectangular: 3 × 2 × 0.15 = 0.9 m³
  • Piers: π × (0.2 m)² × 2.5 = 0.3141593 m³ each × 4 = 1.2566371 m³
  • Calculated volume: 0.9 + 1.2566371 = 2.1566371 m³
  • Concrete to order: 2.1566371 × 1.05 = 2.2644689 m³

Result

2.26 m³ concrete to order.

Practical interpretation

The same method applies in Metric — only the units change.

FAQ

How do I calculate how much concrete I need?
Multiply the dimensions of each pour to get its volume — length × width × height for rectangular shapes, π × radius² × height for round ones — multiply by how many of that shape you're pouring, add every section together, then add an order allowance on top. This calculator does all of that automatically once you enter your sections.
How many cubic yards of concrete do I need?
Divide the total volume in cubic feet by 27. The hero result already shows cubic yards (Imperial) or cubic meters (Metric) directly, with the cubic-foot figure underneath.
Can I combine several concrete pours in one calculation?
Yes — that's what this calculator is for. Add a section for each pour, give each one a quantity, and they're combined into one total and one concrete-to-order figure. You can mix rectangular, round and hollow round sections freely in the same project.
How do I calculate concrete for a round column or pier?
Choose the Round shape and enter the diameter and the height or depth. The calculator halves the diameter to get the radius and applies π × radius² × height. Set the quantity to how many identical columns or piers you're pouring.
How do I calculate concrete for a footing?
Enter footing dimensions from your project's plans as a Rectangular section — length, width and depth — with the quantity set to how many identical footings you have. This calculator converts dimensions you already have into concrete volume; it does not determine footing size, depth, bearing capacity, frost depth, reinforcement or code requirements.
Does this calculator subtract the volume of a post from a post hole?
No. A round section returns the full volume of the hole. If a post occupies part of it, the real concrete requirement is lower — a 4×4 post in a 12-inch hole takes up roughly a ninth of the space. Deduct the post's own volume yourself, or treat the figure as deliberately generous.
How much extra concrete should I order?
NRMCA's guidance suggests roughly 4–10% over the calculated volume, depending on how controlled the placement is — there's no single correct percentage. This calculator defaults to 5% and lets you change it.
How many bags of concrete do I need?
Open Advanced options, enter your bag product's stated mixed yield (or use the QUIKRETE Concrete Mix quick-fills), and the calculator divides your order volume by that yield and rounds up to a whole bag. Bag counts are always based on mixed yield, never on the bag's dry weight.
Should I use this calculator or the Concrete Slab Calculator?
Use this one when the job has several different shapes or repeated objects to multiply — footings, columns, piers, rings. Use the Concrete Slab Calculator when you're pouring flatwork; it's built around area and thickness and adds truckload planning and a ready-mix-versus-bagged cost comparison.
Does this calculator estimate cost?
Optionally, yes — enter a ready-mix price per cubic yard or cubic meter and it multiplies that by your order volume. It's a material-only figure from the price you enter, and excludes delivery, minimum-load and short-load fees, pumping, labor and taxes.