Concrete Footing Calculator
Estimate concrete for continuous strip footings, rectangular isolated footings, and round footings — combine multiple footing sections into one concrete order.
Your Footings
Footing reference diagrams
Footing Sections
1 sectionAdd a section for each footing in your project — continuous, rectangular, or round — and combine them all into one concrete order.
Section 01 of 01
Runs along the length of a wall or similar continuous line. Enter the dimensions your plans call for.
Combining footings with columns, piers, walls or other shapes in one order? Use the Concrete Calculator for mixed-shape projects. Pouring a slab instead of a footing? Use the Concrete Slab Calculator for slab-specific planning.
Advanced options
Order allowance
NRMCA guidance suggests roughly 4-10% over plan volume for waste, over-excavation and placement contingencies — footing/trench work often sees more variation than a formed slab, so adjust this for your project rather than treating 5% as universally correct.
Bagged concrete
Optional. Bag count is based on the mixed yield you enter below, not bag weight — different manufacturers' same-weight bags do not necessarily yield the same mixed volume.
From your product's stated mixed yield — never inferred from bag weight.
Truckload planning
Optional and planning-only. Enter the usable capacity quoted by your supplier — truck capacities and delivery policies vary.
Cost estimate
Entirely optional — no price is pre-filled. Material estimate only; excludes labor, delivery, pumping, taxes, and other charges.
Requires a mixed yield entered above (in Bagged concrete) to produce a bag count.
If both prices are entered, they're shown as separate alternative estimates — ready-mix and bagged concrete are different ways to buy the same concrete, never added together.
Your Estimate
Enter your footing dimensions to see your concrete estimate.
How It's Calculated
Methodology
Enter your footing dimensions to see the formula breakdown.
Assumptions & Accuracy
Footing volume uses plain geometry (length × width × depth for continuous and rectangular footings, π × radius² × depth for round footings). Every section's volume is summed before the order allowance is applied — never rounded or estimated separately. Optional bags, truckloads, and prices use only the values you enter.
Material quantity estimate only. This calculator converts footing dimensions you provide into concrete volume. It does not determine footing width, depth, structural capacity, soil bearing, frost depth, reinforcement, loads, or code compliance.
Project Guide
How to measure a footing
Measure the dimensions your plans or project already specify — a continuous footing's total run length, width, and depth; an isolated footing's length/width or diameter, and its depth. This calculator does not tell you what those numbers should be; it converts the numbers you already have into concrete volume.
Continuous vs. isolated vs. round footing
A continuous (strip) footing runs along the full length of a wall or similar continuous line — a foundation wall, a fence line. A rectangular isolated footing (also called a pad footing) supports a single point load, like a post or column base. A round footing covers a round or pier-shaped footing — common under a deck post or a Sonotube-formed pour. All three are common, and a real project often combines more than one type.
What total strip-footing length means
A continuous footing's “total length” is the entire run — not a single segment repeated. That's why this footing type has no quantity field: the length you enter already covers the whole footing, so a multiplier would double-count it.
How multiple footing sections are combined
Add one section per footing type or run in your project — a strip footing, several pad footings, a handful of round footings. Each section's volume is calculated in full, all sections are added together at full precision, and only then is the order allowance applied once to the combined total. Nothing is rounded section-by-section along the way.
What the order allowance means
Field dimensions rarely match plan dimensions exactly. NRMCA's own technical guidance (CIP 8, “Discrepancies in Yield”) recommends ordering roughly 4-10% over the calculated volume for waste, over-excavation, and placement contingencies — explicitly as a range, not one fixed number. This calculator's 5% default sits in that range but is fully editable.
Why footing/trench excavation may need extra allowance
CIP 8 specifically notes that sporadic, combination work — footings, walls, and incidental fill together — tends to need a bigger allowance than a single controlled, repetitive pour. A hand- or machine-dug footing trench in undisturbed soil often has more over-dig variance than a screeded slab subgrade, so many footing projects sit toward the higher end of the 4-10% range rather than the low end. There is no single correct number for every project — adjust the allowance for your own site conditions.
Bagged concrete vs. ready-mix
Ready-mix concrete is delivered by truck in bulk and suits larger pours where the volume justifies a delivery. Bagged concrete mix is measured and mixed on site bag by bag, and suits smaller footing projects, repairs, or a handful of isolated footings where a full truck delivery isn't practical. Bag counts use your product's manufacturer-stated mixed yield, never a figure guessed from bag weight — two bags of the same weight from different manufacturers do not necessarily yield the same mixed volume.
Truckload planning
Truck capacity is not standardized — it varies by supplier, region, and truck, so this calculator never assumes a figure. Enter the usable capacity your supplier quotes to see how many truck-capacity equivalents your order needs and how many whole truckloads to plan for. This is planning-only: it does not determine supplier minimum orders, short-load charges, or delivery policies.
Which concrete calculator should I use?
Use this calculator when your project is footings only — it uses footing-specific terminology and diagrams, and combines continuous, rectangular, and round footings into one order.
Use the Concrete Calculator when you're combining footings with columns, piers, walls, or other non-footing shapes in one project. Use the Concrete Slab Calculator when you're pouring flatwork instead of a footing.
What this calculator does not design
- Recommended footing width or depth.
- Bearing capacity or soil-bearing calculations.
- Frost-depth requirements.
- Reinforcement or rebar sizing.
- Structural loads or foundation engineering.
- Building code or local requirement compliance.
This calculator takes dimensions you already have — from your drawings, your plans, or a professional — and converts them into concrete volume. Those design decisions belong to your project documents or a qualified professional.
Worked Examples
Illustrative values only — enter your own project's dimensions above for a real estimate.
Example 01
Continuous footing, Imperial: 40 ft total length, 1.5 ft width, 8 in depth, 5% order allowance.
Inputs
- Total length: 40 ft
- Width: 1.5 ft
- Depth: 8 in
- Order allowance: 5%
Calculation
- Depth: 8 ÷ 12 = 0.6667 ft
- Raw volume: 40 × 1.5 × 0.6667 = 40.00 ft³
- Concrete to order: 40.00 × 1.05 = 42.00 ft³
- Concrete to order: 42.00 ÷ 27 = 1.56 yd³
Result
Practical interpretation
Example 02
Mixed footing project: a continuous footing plus rectangular isolated pads plus round isolated footings, combined into one order.
Inputs
- Strip footing: 40 ft total length × 1.5 ft width × 8 in depth
- Pad footings: 3 ft × 3 ft × 1 ft, quantity 4
- Round footings: 1.5 ft diameter × 1 ft depth, quantity 6
- Order allowance: 5%
Calculation
- Strip footing: 40 × 1.5 × 0.6667 = 40.00 ft³
- Pad footings: 3 × 3 × 1 × 4 = 36.00 ft³
- Round footings: π × 0.75² × 1 × 6 = 10.60 ft³
- Total raw volume: 40.00 + 36.00 + 10.60 = 86.60 ft³
- Concrete to order: 86.60 × 1.05 = 90.93 ft³
- Concrete to order: 90.93 ÷ 27 = 3.37 yd³
Result
Practical interpretation
FAQ
How much concrete do I need for a footing?
How do I calculate concrete for a strip footing?
What is the difference between a strip footing and an isolated footing?
How do I calculate concrete for a round footing?
Can I combine several footing types in one calculation?
How much extra concrete should I allow?
How many bags of concrete do I need?
Can this calculator estimate ready-mix truckloads?
How wide or deep should my footing be?
Does this calculator design footing reinforcement?
Should I use the Footing Calculator or the General Concrete Calculator?
Should I use the Footing Calculator or Concrete Slab Calculator?
Related Calculators
Concrete & Masonry
Concrete Calculator
Estimate concrete volume for columns, piers, walls, footings and other pours. Combine several different shapes into one project and calculate one concrete order with an editable order allowance.
Concrete & Masonry
Concrete Slab Calculator
Estimate how much concrete to order for a rectangular or circular slab, plus optional bags, truckloads, and material cost.